Business Challenge

Bidvest Panalpina Logistics was up for a data center refresh but where looking to reduced operational overhead and reduce costs on the Data Center go forward.

PROJECT

DC Migration to Azure

CUSTOMER

Bidvest Panalpina Logistics

YEAR

2017

INDUSTRY

Logistics

Project Outcome

BPL made the decision to move the Data Center into Azure.

BUI were contracted to Migrate from VMWare to Hyper-V on premises, then migrated their entire data center in Azure

Cloud Strategy

Assessment of the on-premises environment and workshop to define migration strategy

Cloud Methodology

Cloud Methodology defined and tested

Technical Roadmap

Defined technical requirements and design documentation

Azure Migration

Migrate workloads from VMWare to Hyper-V on-premises, once completed, all workloads where migrated into Azure.

BUI Bidvest Panalpina Logistics Case study Number 2

Deliverables

 

Azure discovery and best practices

Scope solution with customer

Migrated Data Center

Reduce on-premises foot print